Spaghetti Junction ramp expected to open next week

LOUISVILLE — Repairs on a deteriorated support column for the ramp that carries traffic from Interstate 65 North to I-64 West is nearing completion, with concrete scheduled to be poured this weekend.

The ramp is expected to reopen to traffic early next week, after this week’s work was slowed by snow and ice, according to a press release from Ohio River Bridges Projects officials.

The ramp closed last weekend, allowing Walsh Construction Co., leader of the design-build team that is constructing the new downtown bridge, to begin repairs. Crews are removing the deteriorated concrete, replacing damaged steel rebar and pouring a new layer of concrete around the column to encase the repaired core, the release says.

The entire ramp will be torn down and replaced in 2015 as part of the reconstruction of the Kennedy Interchange, which is a major part of the downtown project.

1
Text Only | Photo Reprints
Bridges Project
LOCAL MAGAZINES
Easter 2014 photos


Click on any photo to purchase it.

SPECIAL CONTENT
Twitter Updates
Follow us on twitter
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
AP Video
Netanyahu Vows to Destroy Hamas Tunnels Obama Slams Republicans Over Lawsuit House Leaders Trade Blame for Inaction Malaysian PM: Stop Fighting in Ukraine Cantor Warns of Instability, Terror in Farewell Ravens' Ray Rice: 'I Made a Huge Mistake' Florida Panther Rebound Upsets Ranchers Small Plane Crash in San Diego Parking Lot Busy Franco's Not Afraid of Overexposure Fighting Blocks Access to Ukraine Crash Site Dangerous Bacteria Kills One in Florida Workers Dig for Survivors After India Landslide Texas Scientists Study Ebola Virus Smartphone Powered Paper Plane Debuts at Airshow Southern Accent Reduction Class Cancelled in TN
2013 Photos of the year


Take a look at our most memorable photos from 2013.