Lack of public at hearing for Jeffersonville sewer project

$34.4 million project up for review

JEFFERSONVILLE — A public hearing to discuss the Combined Sewer Overflow sewer project in Jeffersonville was held recently with no members of the public present.

The combined sewer overflow project is an estimated $34 million plan to comply with an Environmental Protection Agency agreed order issued in 2009.

Engineer Josh Hillman, with Jacobi, Toombs and Lanz, Inc. said the city is submitting a preliminary engineering report to the State Revolving Loan fund, which requires a public hearing take place.

The CSO interceptor project is expected to bring the city into compliance with the agreed order signed with the EPA in 2009 to eliminate sewer overflows. Those overflows occurred when heavy rainfall washed untreated sewage into area waterways, violating the Clean Water Act.

The plan to install only an interceptor pipe became the focus of the Mayor Mike Moore’s administration, which replaced a plan from former Mayor Tom Galligan to install a $65 million canal through downtown. The canal plan was designed to solve the overflow problem and ease flooding, and the interceptor pipe had always been a part of the project.

The estimated cost to install the interceptor pipe was $30.8 million and was based on feet of pipe, along with a contingency amount, Hillman said.

With a more detailed version of the plan including the cost for structures, asphalt and pipe, a revised estimated total equaled $34.4 million.

Hillman said the project calls for the installation of a new interceptor sewer parallel to the Ohio River that will connect the existing overflows to a new, oversized interceptor. In addition, an interceptor will be placed in the north-south corridor that carries wastewater to the 10th Street pumping station.

He said there are four options that will be considered in the draft documents. The alternatives being considered are to run the sewer lines along Market and Mulberry streets; Chestnut and Mulberry streets or Chestnut and Watt streets.

“The final alignment for the combined sewer overflow interceptor will not be determined until we get into final design,” Hillman said.

Plans presented at the public hearing will be available for review at the Jeffersonville Public Library, the city clerk’s office and at the wastewater superintendents office through Friday, Nov. 30.

The SRF loan is a 20-year loan and will be paid back through increased rates to city sewer bills that were approved by the city council in 2009.

The sewer rate increases approved by the Jeffersonville City Council in 2009 will continue to be phased in. The latest phase of the increase took the average bill to around $55 starting in 2012. Additional increases planned in 2013, 2014 and 2015 will take the average bill to about $73.

1
Text Only | Photo Reprints

LOCAL MAGAZINES
Easter 2014 photos


Click on any photo to purchase it.

LOCAL STATISTICS
Twitter Updates
Follow us on twitter
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
AP Video
Bon Jovi Helps Open Low-income Housing in Philly Pipeline Opponents Protest on National Mall Hagel Gets Preview of New High-tech Projects S.C. Man Apologizes for Naked Walk in Wal-Mart New Country Music Hall of Fame Inductees Named 'Piles' of Bodies in South Sudan Slaughter New Yorkers Celebrate Cherry Blossom Blooms SCOTUS Hears Tv-over-Internet Case Justice Dept. Broadening Criteria for Clemency Chief Mate: Crew Told to Escape After Passengers 'Miss Meadows' Takes Holmes Back to Her Roots Biden: Russia Must Stop Talking, Start Acting David Moyes Out As Manchester United Manager Raw: Leopard Bites Man in India Iowa College Finds Beauty in Bulldogs High Court to Hear Dispute of TV Over Internet Stowaway Teen Forces Review of Airport Security
2013 Photos of the year


Take a look at our most memorable photos from 2013.